REEVES • S14677-01

06DEC
Fabrication
The frame will be constructed, the compartments are fabricated and the body will be assembled.

13DEC
Fabrication
The frame will be constructed, the compartments are fabricated and the body will be assembled.

15DEC
Fabrication
The frame will be constructed, the compartments are fabricated and the body will be assembled.

20DEC
Electrical
The wiring harness is installed. Emergency and scene lighting are mounted and terminated at the breaker panel.

22DEC
Electrical
The wiring harness is installed. Emergency and scene lighting are mounted and terminated at the breaker panel.







19JAN
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.


24JAN
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.


26JAN
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.


07FEB
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.


14FEB
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.


16FEB
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.

21FEB
Chassis Prep
The bumper is replaced, cab consoles are fitted and the suspension upgrade package and tires are installed.

02MAR
Assembly
The body will be mounted to the chassis, final plumbing and electrical connections are made.

14MAR
Assembly
The body will be mounted to the chassis, final plumbing and electrical connections are made.